The Integrated Reporting of Wildland-Fire Information (IRWIN) investment is a Department of the Interior managed application. It will follow all relevant capital planning and investment guidelines for the Department of the Interior.
The lifecycle of the IRWIN investment is planned through Fiscal Year 2026.
Extended Team Project Plan
The IRWIN Extended Team Project Management Plan is the top-level controlling document for the IRWIN project. This project plan defines the framework in which the IRWIN project will be executed. It defines the technical and managerial processes required to complete the project and meet the requirements as defined by the wildland fire business community. This plan is updated annually.
- IRWIN Project Management Plan Extended Team (PDF, 290 MB)
Engagement and Timing
The following applications are priorities for data exchange through IRWIN. The associated dates are based on current understanding of priority and ability to integrate. These will be adjusted, as needed, based on stakeholder and application team input.
System | Discovery | Development | Operations & Maintenance |
---|---|---|---|
WildCAD | 2012 | 2013 | 2014 |
FireCode | 2012 | 2013 | 2014 |
Incident Command System (ICS) 209 | 2012 | 2013 | 2014 |
Wildland Fire Decision Support System (WFDSS) | 2012 | 2013 | 2014 |
Integrated Fire Management - Alaska Computer Aided Dispatch (CAD) | 2013 | 2013 | 2014 |
Dispatch Tracker - Texas Computer Aided Dispatch (CAD) | 2013 | 2014 | 2014 |
National Wildfire Coordinating Group (NWCG) UNIT ID | 2013 | 2014 | 2015 |
e-ISuite (Read Only) | 2013 | 2014 | 2015 |
FIRESTAT (Read Only) | 2014 | 2015 | 2016 |
INFORM – Next Generation Wildland Fire Management Information-Fire Reporting Module (WFMI–FR) | 2017 | 2017 | 2019 |
National Fire Plan Operations and Reporting System (NFPORS) | 2017 | 2018 | 2019 |
Forest Service Activity Tracking Support (FACTS) | 2017 | 2018 | 2019 |
Interagency Resource Ordering Capability (IROC) | 2017 | 2018/2019 | 2020 |
Other CAD applications | When available and/or as the schedule allows |